SUBSECRETARIA DE INFRAESTRUCTURA |
DIRECCION GENERAL DE CONSERVACION DE CARRETERAS |
Programa Nacional de Conservación de Carreteras |
Avance Fìsico - Financiero |
|
|
|
|
|
|
DICIEMBRE 2019 |
NOMBRE DE LA OBRA |
UBICACIÓN |
META |
ASIGNACION |
AVANCE FISICO |
AVANCE FINANCIERO |
Km Inicial |
Km Final |
UNIDAD |
% |
BAJA CALIFORNIA SUR |
|
|
|
479,415,930.95 |
|
100.00 |
99.15 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Costa Azul (Cabo San Lucas - La Paz) |
102+200 |
1.00 |
13,037,349.48 |
1.00 |
100.00 |
100.00 |
Tiburón Der. (Cabo San Lucas - La Paz) |
9+600 |
1.00 |
10,922,959.18 |
1.00 |
100.00 |
100.00 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Recuperación de Pavimentos y Carpeta |
|
|
5.00 |
27,996,347.35 |
5.00 |
100.00 |
100.00 |
Santa Rosalía - Paralelo 28 |
211.00 |
216.00 |
5.00 |
27,996,347.35 |
5.00 |
100.00 |
100.00 |
|
|
|
|
|
|
|
|
Fresado y Carpeta de 5.0 cm |
|
|
4.00 |
13,233,971.10 |
4.00 |
100.00 |
100.00 |
San Pedro - Todos Santos - Cabo San Lucas (Cpo. A) |
111.00 |
115.00 |
4.00 |
13,233,971.10 |
4.00 |
100.00 |
100.00 |
|
|
|
|
|
|
|
|
Riego de Sello |
|
|
268.00 |
165,206,837.58 |
268.00 |
100.00 |
100.00 |
Cabo San Lucas - La Paz (Cpo. A) |
16.00 |
20.00 |
4.00 |
3,091,237.74 |
4.00 |
100.00 |
100.00 |
Cabo San Lucas - La Paz (Cpo. B) |
21.00 |
24.00 |
3.00 |
2,318,428.30 |
3.00 |
100.00 |
100.00 |
Cabo San Lucas - La Paz (Cpo. B) |
31.00 |
43.00 |
12.00 |
9,273,713.21 |
12.00 |
100.00 |
100.00 |
Cabo San Lucas - La Paz |
132.00 |
152.00 |
20.00 |
11,184,972.28 |
20.00 |
100.00 |
100.00 |
San Pedro - Todos Santos - Cabo San Lucas (2 Cpos.) |
15.00 |
16.00 |
2.00 |
1,403,218.50 |
2.00 |
100.00 |
100.00 |
San Pedro - Todos Santos - Cabo San Lucas (2 Cpos.) |
38.00 |
46.00 |
16.00 |
11,225,747.96 |
16.00 |
100.00 |
100.00 |
San Pedro - Todos Santos - Cabo San Lucas (2 Cpos.) |
71.00 |
77.00 |
12.00 |
8,513,045.50 |
12.00 |
100.00 |
100.00 |
San Pedro - Todos Santos - Cabo San Lucas (2 Cpos.) |
77.00 |
80.00 |
6.00 |
4,256,522.75 |
6.00 |
100.00 |
100.00 |
San Pedro - Todos Santos - Cabo San Lucas (2 Cpos.) |
80.00 |
96.00 |
32.00 |
20,981,820.80 |
32.00 |
100.00 |
100.00 |
La Paz - Cd. Insurgentes |
70.00 |
85.00 |
15.00 |
9,649,045.17 |
15.00 |
100.00 |
100.00 |
La Paz - Cd. Insurgentes |
125.00 |
139.00 |
14.00 |
8,178,757.61 |
14.00 |
100.00 |
100.00 |
Loreto - Santa Rosalía |
30.00 |
40.00 |
10.00 |
6,670,730.85 |
10.00 |
100.00 |
100.00 |
Loreto - Santa Rosalía |
136.00 |
147.00 |
11.00 |
7,625,211.59 |
11.00 |
100.00 |
100.00 |
Santa Rosalía - Paralelo 28 |
7.00 |
13.00 |
6.00 |
3,910,076.38 |
6.00 |
100.00 |
100.00 |
Santa Rosalía - Paralelo 28 |
35.00 |
53.00 |
18.00 |
10,614,971.21 |
18.00 |
100.00 |
100.00 |
Santa Rosalía - Paralelo 28 |
85.00 |
95.00 |
10.00 |
7,015,605.89 |
10.00 |
100.00 |
100.00 |
Santa Rosalía - Paralelo 28 |
165.00 |
189.00 |
24.00 |
13,834,475.55 |
24.00 |
100.00 |
100.00 |
Santa Rosalía - Paralelo 28 |
189.00 |
214.00 |
25.00 |
15,766,304.16 |
25.00 |
100.00 |
100.00 |
San Pedro - Todos Santos - Cabo San Lucas (Cpo. A) |
57.00 |
71.00 |
14.00 |
4,693,838.61 |
14.00 |
100.00 |
100.00 |
San Pedro - Todos Santos - Cabo San Lucas (Cpo. B) |
57.00 |
71.00 |
14.00 |
4,999,113.52 |
14.00 |
100.00 |
99.99 |
|
|
|
|
|
|
|
|
Riego de Protección |
|
|
64.00 |
11,959,434.42 |
64.00 |
100.00 |
100.00 |
La Paz - Cd. Insurgentes (ASI) |
105.00 |
125.00 |
20.00 |
3,438,699.64 |
20.00 |
100.00 |
100.00 |
La Paz - Cd. Insurgentes (Nanosello) |
85.00 |
105.00 |
25.00 |
3,494,875.64 |
20.00 |
100.00 |
99.99 |
Loreto - Santa Rosalía (Nanosello) |
16.30 |
40.50 |
24.00 |
5,025,859.14 |
24.00 |
100.00 |
100.00 |
|
|
|
|
|
|
|
|
Conservación Periódica de Puentes |
|
|
4.00 |
5,695,149.34 |
4.00 |
100.00 |
100.00 |
|
|
|
|
|
|
|
|
Señalamiento Horizontal (Lineal del Estado) |
|
|
1,199.60 |
47,877,199.61 |
1,199.60 |
100.00 |
100.00 |
|
|
|
|
|
|
|
|
Barrera de Protección |
|
|
17,370.00 |
14,960,112.08 |
17,370.00 |
100.00 |
100.00 |
Barrera de Protección (contrato no.047) |
|
|
8,685.00 |
8,438,458.12 |
8,685.00 |
100.00 |
100.00 |
Barrera de Protección (contrato no.048) |
|
|
8,685.00 |
6,521,653.96 |
8,685.00 |
100.00 |
100.00 |
|
|
|
|
|
|
|
|
Señalamiento Vertical |
|
|
6,750.00 |
20,648,012.56 |
6,750.00 |
100.00 |
100.00 |
Señalamiento Vertical (contrato no.045) |
|
|
3,375.00 |
9,977,467.99 |
3,375.00 |
100.00 |
100.00 |
Señalamiento Vertical (contrato no.046) |
|
|
3,375.00 |
10,670,544.57 |
3,375.00 |
100.00 |
100.00 |
|
|
|
|
|
|
|
|
Conservación Rutinaria de Puentes (contrato no.009) |
|
|
82.00 |
3,893,753.79 |
82.00 |
100.00 |
100.00 |
Conservación Rutinaria de Puentes (contrato no.010) |
|
|
80.00 |
3,697,788.21 |
80.00 |
100.00 |
100.00 |
|
|
|
|
|
|
|
|
Estudios y/o Proyectos |
|
|
|
1,445,510.480 |
|
|
80.65 |
Estudios y/o Proyectos |
|
|
|
694,903.63 |
|
|
100.00 |
Seguimiento (contrato no.017) |
|
|
|
3,810,532.00 |
|
|
100.00 |
|
|
|
|
|
|
|
|