SUBSECRETARIA DE INFRAESTRUCTURA |
DIRECCION GENERAL DE CONSERVACION DE CARRETERAS |
Programa Nacional de Conservación de Carreteras |
Avance Fìsico - Financiero |
|
|
|
|
|
|
DICIEMBRE 2019 |
NOMBRE DE LA OBRA |
UBICACIÓN |
META |
ASIGNACION |
AVANCE FISICO |
AVANCE FINANCIERO |
Km Inicial |
Km Final |
UNIDAD |
% |
CHIHUAHUA |
|
|
|
616,714,073.88 |
|
94.34 |
93.47 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
PIV Rosetilla (Delicias - Chihuahua) |
138+900 |
1.00 |
2,554,689.14 |
1.00 |
100.00 |
99.97 |
Sacramento I (Chihuahua - Sueco) |
12+900 |
1.00 |
11,933,022.78 |
1.00 |
100.00 |
100.00 |
El Tecolotle (Aldama-Ojinagua) |
221+300 |
1.00 |
2,605,345.42 |
1.00 |
100.00 |
100.00 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Bacheo y Carpeta de 5.0 cm |
|
|
6.50 |
17,571,976.09 |
6.05 |
93.08 |
100.00 |
Hidalgo del Parral - Puerto Sabinal |
150.00 |
156.50 |
6.50 |
17,571,976.09 |
6.05 |
93.08 |
100.00 |
|
|
|
|
|
|
|
|
Fresado y Carpeta de 5.0 cm |
|
|
46.00 |
84,944,274.85 |
43.30 |
93.27 |
92.92 |
TimbralCuauhtémoc - Lím. de Edos. Chih./Son. |
210.00 |
217.00 |
7.00 |
11,900,330.79 |
5.80 |
82.86 |
62.24 |
Villa Ahumada - Cd. Juarez (Cpo. A) mezcla de alto desempeño |
283.00 |
288.00 |
5.00 |
7,717,232.70 |
5.00 |
100.00 |
100.00 |
Villa Ahumada - Cd. Juarez (Cpo. B) mezcla de alto desempeño |
298.00 |
314.00 |
16.00 |
22,739,900.89 |
16.00 |
100.00 |
100.00 |
Delicias - Chihuahua (Cpo. A) mezcla de alto desempeño |
142.00 |
150.00 |
8.00 |
18,113,260.80 |
8.00 |
100.00 |
91.61 |
Delicias- Chihuahua (Cpo. B) |
140.00 |
146.00 |
6.00 |
13,969,147.61 |
5.50 |
91.67 |
100.00 |
Delicias- Chihuahua (Cpo. B) |
146.00 |
150.00 |
4.00 |
9,896,243.91 |
3.00 |
75.00 |
100.00 |
Delicias- Chihuahua (Cpo. A) |
137.00 |
142.00 |
finiquito |
608,158.15 |
|
|
100.00 |
|
|
|
|
|
|
|
|
Renivelación y Riego de Sello |
|
|
107.50 |
79,927,650.78 |
102.00 |
95.36 |
95.01 |
Janos - Lím. de Edos. Chih./Son. |
62.00 |
73.50 |
11.50 |
8,923,673.57 |
11.50 |
100.00 |
99.51 |
Janos - Lím. de Edos. Chih./Son. |
4.00 |
27.00 |
23.00 |
16,777,342.30 |
23.00 |
100.00 |
100.00 |
Chihuahua - El Sueco (Cpo. A) |
31.00 |
43.00 |
12.00 |
8,956,129.29 |
12.00 |
100.00 |
99.15 |
Juárez - Janos |
70.00 |
84.00 |
14.00 |
10,636,489.92 |
14.00 |
100.00 |
99.87 |
Cuauhtémoc - Lím. de Edos. Chih./Son. |
220.00 |
240.00 |
20.00 |
13,477,599.18 |
14.50 |
72.50 |
71.37 |
Juárez - Janos |
84.00 |
104.00 |
20.00 |
14,800,905.12 |
20.00 |
100.00 |
100.00 |
Hidalgo del Parral - Puerto Sabinal |
10.00 |
17.00 |
7.00 |
6,355,511.40 |
7.00 |
100.00 |
100.00 |
|
|
|
|
|
|
|
|
Renivelación |
|
|
61.50 |
64,473,821.93 |
47.00 |
75.97 |
90.45 |
Nuevo Palomas -Hidalgo del Parral (Vía Corta) |
88.00 |
92.00 |
4.00 |
6,333,960.99 |
4.00 |
100.00 |
100.00 |
Hidalgo del Parral - Puerto Sabinal |
42.00 |
52.00 |
10.00 |
11,274,776.65 |
10.00 |
100.00 |
98.96 |
Chihuahua – El Sueco |
31.00 |
45.00 |
14.00 |
12,052,832.68 |
14.00 |
100.00 |
93.07 |
Lim. de Edos. Dgo./Chih. - Jimenez |
163.00 |
170.00 |
7.00 |
9,991,975.06 |
3.50 |
50.00 |
51.19 |
Cuauhtémoc- Lim. De Edos./Son. Cpo. "B" |
139.00 |
145.00 |
6.00 |
9,289,901.76 |
3.50 |
58.33 |
100.00 |
Villa Ahumada - Cd. Juárez |
292.50 |
298.00 |
5.50 |
7,560,878.99 |
3.00 |
54.55 |
95.70 |
Aldama- Ojinaga |
117.00 |
132.00 |
15.00 |
7,969,495.80 |
9.00 |
60.00 |
100.00 |
|
|
|
|
|
|
|
|
Microaglomerado |
|
|
10.00 |
9,554,200.80 |
10.00 |
100.00 |
100.00 |
El Sueco - Janos |
10.00 |
20.00 |
10.00 |
9,554,200.80 |
10.00 |
100.00 |
100.00 |
|
|
|
|
|
|
|
|
Riego de Protección |
|
|
47.00 |
6,065,686.40 |
47.00 |
100.00 |
100.00 |
Lim. de Edos. Dgo./Chih. - H. del Parral |
382.30 |
406.60 |
22.00 |
2,886,822.40 |
22.00 |
100.00 |
100.00 |
Aldama- Ojinaga |
92.00 |
117.00 |
25.00 |
3,178,864.00 |
25.00 |
100.00 |
100.00 |
|
|
|
|
|
|
|
|
Conservación Periódica de Puentes |
|
|
11.00 |
4,131,915.39 |
11.00 |
100.00 |
100.00 |
|
|
|
|
|
|
|
|
El Morrión - Coyamito |
93+000 |
1.00 |
8,999,454.00 |
0.55 |
55.00 |
100.00 |
|
|
|
|
|
|
|
|
Conservación Rutinaria de Tramos (Lineal del Estado) |
|
|
2,111.42 |
189,809,473.72 |
2,111.42 |
100.00 |
98.13 |
Gastos de Operación |
|
|
|
8,630,856.00 |
|
|
0.00 |
|
|
|
|
|
|
|
|
Señalamiento Horizontal (Lineal del Estado) |
|
|
2,111.42 |
48,330,470.66 |
2,111.42 |
100.00 |
86.88 |
|
|
|
|
|
|
|
|
Barrera de Protección (contrato no.___) |
|
|
5,134.00 |
4,301,831.22 |
5,134.00 |
100.00 |
78.24 |
Barrera de Protección (contrato no.___) |
|
|
5,142.00 |
3,405,121.93 |
1,150.00 |
22.36 |
30.00 |
|
|
|
|
|
|
|
|
Señalamiento Vertical (contrato no. 055) |
|
|
3,480.00 |
9,578,464.75 |
3,350.00 |
96.26 |
93.90 |
Señalamiento Vertical (contrato no. 056) |
|
|
3,480.00 |
9,313,846.56 |
3,480.00 |
100.00 |
99.96 |
Señalamiento Vertical (contrato no. 057) |
|
|
3,480.00 |
14,020,540.56 |
3,480.00 |
100.00 |
99.98 |
|
|
|
|
|
|
|
|
Conservación Rutinaria de Puentes (contrato no. 021) |
|
|
125.00 |
4,899,992.25 |
125.00 |
100.00 |
100.00 |
Conservación Rutinaria de Puentes (contrato no. 022) |
|
|
101.00 |
4,007,861.24 |
101.00 |
100.00 |
95.01 |
Conservación Rutinaria de Puentes (contrato no. 023) |
|
|
166.00 |
6,092,246.39 |
166.00 |
100.00 |
100.00 |
|
|
|
|
|
|
|
|
Estudios y/o Proyectos |
|
|
|
1,500,000.00 |
|
|
0.00 |
Estudios y/o Proyectos |
|
|
|
3,713,106.00 |
|
|
100.00 |
Seguimiento |
|
|
|
3,997,774.00 |
|
|
100.00 |
Seguimiento |
|
|
|
3,997,774.00 |
|
|
99.99 |
|
|
|
|
|
|
|
|