SUBSECRETARIA DE INFRAESTRUCTURA |
DIRECCION GENERAL DE CONSERVACION DE CARRETERAS |
Programa Nacional de Conservación de Carreteras |
Avance Fìsico - Financiero |
|
|
|
|
|
|
DICIEMBRE 2019 |
NOMBRE DE LA OBRA |
UBICACIÓN |
META |
ASIGNACION |
AVANCE FISICO |
AVANCE FINANCIERO |
Km Inicial |
Km Final |
UNIDAD |
% |
JALISCO |
|
|
|
721,082,136.00 |
|
98.64 |
94.92 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Penitenciaria (Zapotlanejo - Guadalajara) |
175+121 |
1.00 |
15,136,717.42 |
1.00 |
100.00 |
100.00 |
Pegueros I (Lagos de Moreno - Zapotlanejo) |
99+600 |
1.00 |
11,498,614.75 |
1.00 |
100.00 |
100.00 |
P. P. Villa Corona (Ent. Acatlán - Autlán) |
13+700 |
1.00 |
3,085,335.01 |
1.00 |
100.00 |
99.99 |
Reconstrucción de Puentes |
|
|
finiquito |
352,633.84 |
|
|
100.00 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Bacheo y Carpeta de 5.0 cm |
|
|
101.08 |
191,397,972.45 |
101.08 |
100.00 |
98.78 |
Autlán - Barra de Navidad (T.A.) |
157.32 |
173.00 |
10.00 |
18,341,776.15 |
10.00 |
100.00 |
100.00 |
Ameca - Mascota (T.A.) |
102.00 |
118.00 |
6.60 |
11,095,700.78 |
6.60 |
100.00 |
99.96 |
Guadalajara - Tepic (2 Cpos.) T.A. (incluye renivelaciones) (a) |
9.00 |
25.00 |
27.50 |
59,005,836.30 |
27.50 |
100.00 |
100.00 |
Libramiento Lagos de Moreno (incluye renivelaciones) (a) |
0.00 |
13.00 |
13.00 |
22,571,010.13 |
13.00 |
100.00 |
100.00 |
Guadalajara-Santa Rosa(Cpo A) T.A. (incluye renivelaciones) (a) |
4.20 |
25.70 |
19.08 |
34,155,000.00 |
19.08 |
100.00 |
98.30 |
Guadalajara-Santa Rosa(Cpo.B) T.A.* (incluye renivelaciones) (a) |
4.20 |
25.70 |
24.90 |
46,228,649.09 |
24.90 |
100.00 |
96.21 |
|
|
|
|
|
|
|
|
Fresado de 4.0 cm y Carpeta de 9.0 cm |
|
|
14.20 |
49,441,911.51 |
14.20 |
100.00 |
98.81 |
T. Acatlán- Guadalajara (2 Cpos. ) T.A. Mezcla de alto desempeño |
118.00 |
135.00 |
14.20 |
49,441,911.51 |
14.20 |
100.00 |
98.81 |
|
|
|
|
|
|
|
|
Fresado de 5.0 cm y Carpeta de 7.0 cm |
|
|
2.50 |
6,159,229.72 |
2.50 |
100.00 |
99.99 |
Ramal a Yahualica |
2.00 |
4.50 |
2.50 |
6,159,229.72 |
2.50 |
100.00 |
99.99 |
|
|
|
|
|
|
|
|
Riego de Sello |
|
|
53.22 |
12,927,767.02 |
53.22 |
100.00 |
100.00 |
Ent. Santa Rosa - La barca (2 Cpos. ) |
0.00 |
6.00 |
12.00 |
2,154,627.82 |
12.00 |
100.00 |
100.00 |
Lim. Mich/Jal - Ent. Acatlan (2 Cpos. ) |
100.50 |
109.00 |
17.00 |
2,154,627.84 |
17.00 |
100.00 |
100.00 |
El Mirador - El Zapota |
0.00 |
6.00 |
6.00 |
2,154,627.84 |
6.00 |
100.00 |
100.00 |
Ameca - Mascota |
78.00 |
83.82 |
5.82 |
2,154,627.84 |
5.82 |
100.00 |
100.00 |
Ent. Periferico - Ent. Santa Rosa (Cpo A) |
4.60 |
7.00 |
2.40 |
2,154,627.84 |
2.40 |
100.00 |
100.00 |
Ameca - Lim Edos Jal/Nay |
60.00 |
70.00 |
10.00 |
2,154,627.84 |
10.00 |
100.00 |
100.00 |
|
|
|
|
|
|
|
|
Renivelación y Riego de Sello |
|
|
112.30 |
131,748,700.30 |
112.30 |
100.00 |
98.07 |
T. Ameca - Ameca (2 Cpos.) T.A. |
13.80 |
32.00 |
18.00 |
19,938,216.73 |
18.00 |
100.00 |
92.10 |
Lim. de Edos Mich./Jal. - T. Acatlán (T.A.) |
77.40 |
114.80 |
7.10 |
7,864,518.84 |
7.10 |
100.00 |
92.22 |
T. Ameca -Lím. de Edos. Jal./Nay. |
38.00 |
51.00 |
13.00 |
14,079,537.63 |
13.00 |
100.00 |
99.98 |
Ameca - Mascota (T.A.) |
52.00 |
63.00 |
6.60 |
7,753,841.75 |
6.60 |
100.00 |
100.00 |
Ramal a Yahualica (T.A.) |
0.00 |
60.00 |
20.00 |
22,733,471.46 |
20.00 |
100.00 |
100.00 |
Lagos de Moreno - Entr. Yahualica (Cpo. B) |
56.00 |
62.00 |
6.00 |
7,417,584.92 |
6.00 |
100.00 |
100.00 |
Lagos de Moreno - Entr. Yahualica (Cpo. B) |
36.80 |
43.70 |
6.90 |
8,551,473.66 |
6.90 |
100.00 |
99.99 |
Lím. de Edos. Gto./Jal. - Ojuelos |
187.00 |
197.20 |
10.20 |
12,402,650.91 |
10.20 |
100.00 |
99.98 |
Encarnación de Díaz - Aguascalientes |
89.00 |
99.00 |
10.00 |
13,099,518.38 |
10.00 |
100.00 |
100.00 |
Lagos de Moreno - Encarnación de Díaz |
76.00 |
86.00 |
10.00 |
13,109,546.02 |
10.00 |
100.00 |
99.88 |
T. Acatlán - Barra de Navidad |
122.00 |
126.50 |
4.50 |
4,798,340.00 |
4.50 |
100.00 |
93.02 |
|
|
|
|
|
|
|
|
Conservación Periódica de Puentes |
|
|
25.00 |
5,000,000.00 |
25.00 |
100.00 |
99.40 |
|
|
|
|
|
|
|
|
Lím. de Edos. Zac./Jal. - Lagos de Moreno |
125+000 |
126+000 |
1.00 |
1,656,985.73 |
1.00 |
100.00 |
99.93 |
Guadalajara - Lím. de Edos. Jal./Zac. |
49+000 |
50+000 |
1.00 |
1,177,420.67 |
1.00 |
100.00 |
100.00 |
Lím. de Edos. Mich./Jal. - Zapotlanejo |
215+000 |
216+000 |
1.00 |
1,225,553.58 |
1.00 |
100.00 |
100.00 |
Santa Rosa - La Barca |
46+000 |
47+000 |
1.00 |
4,890,416.80 |
1.00 |
100.00 |
100.00 |
Guadalajara - Lím. de Edos. Jal./Nay. |
42+000 |
43+000 |
1.00 |
1,949,383.69 |
1.00 |
100.00 |
93.69 |
Guadalajara - Lím. de Edos. Jal./Nay. |
64+000 |
65+000 |
1.00 |
1,184,234.35 |
1.00 |
100.00 |
99.98 |
Guadalajara - Lím. de Edos. Jal./Zac. |
16+000 |
17+000 |
1.00 |
4,077,996.99 |
1.00 |
100.00 |
87.37 |
Puente Peatonal (Zapotlanejo - Guadalajara) |
184+000 |
1.00 |
4,947,051.39 |
1.00 |
100.00 |
100.00 |
Puente Peatonal (Santa Rosa - La Barca) |
43+000 |
1.00 |
4,984,782.11 |
1.00 |
100.00 |
100.00 |
|
|
|
|
|
|
|
|
Conservación Rutinaria de Tramos (Lineal del Estado) |
|
|
1,955.60 |
152,205,564.46 |
1,955.60 |
100.00 |
90.13 |
Finiquitos 2018 |
|
|
finiquito |
384,504.22 |
|
|
100.00 |
Finiquitos 2018 |
|
|
finiquito |
288,176.66 |
|
|
100.00 |
Finiquitos 2018 |
|
|
finiquito |
154,751.78 |
|
|
100.00 |
Finiquitos 2018 |
|
|
finiquito |
173,906.88 |
|
|
100.00 |
Finiquitos 2018 |
|
|
finiquito |
313,306.47 |
|
|
100.00 |
Finiquitos 2018 |
|
|
finiquito |
387,884.87 |
|
|
100.00 |
Finiquitos 2018 |
|
|
finiquito |
153,234.17 |
|
|
100.00 |
Finiquitos 2018 |
|
|
finiquito |
221,550.89 |
|
|
100.00 |
Finiquitos 2018 |
|
|
finiquito |
219,201.43 |
|
|
100.00 |
Finiquitos 2018 |
|
|
finiquito |
213,172.58 |
|
|
100.00 |
Finiquitos 2018 |
|
|
finiquito |
260,441.31 |
|
|
100.00 |
Finiquitos 2018 |
|
|
finiquito |
171,069.49 |
|
|
100.00 |
Finiquitos 2018 |
|
|
finiquito |
241,074.76 |
|
|
100.00 |
Finiquitos 2018 |
|
|
finiquito |
170,750.47 |
|
|
100.00 |
Finiquitos 2018 |
|
|
finiquito |
182,589.50 |
|
|
100.00 |
Finiquitos 2018 |
|
|
finiquito |
180,583.54 |
|
|
100.00 |
Finiquitos 2018 |
|
|
finiquito |
310,420.11 |
|
|
100.00 |
Finiquitos 2018 |
|
|
finiquito |
293,789.82 |
|
|
100.00 |
Finiquitos 2018 |
|
|
finiquito |
289,820.65 |
|
|
100.00 |
Finiquitos 2018 |
|
|
finiquito |
202,764.14 |
|
|
100.00 |
Finiquitos 2018 |
|
|
finiquito |
196,152.58 |
|
|
100.00 |
Gastos de Operación |
|
|
|
6,520,278.00 |
|
|
86.17 |
|
|
|
|
|
|
|
|
Señalamiento Horizontal (Lineal del Estado) |
|
|
1,955.60 |
25,830,560.00 |
1,887.51 |
96.52 |
100.00 |
|
|
|
|
|
|
|
|
Barrera de Protección (contrato no. 078) |
|
|
4,773.00 |
8,190,875.61 |
0.00 |
0.00 |
26.55 |
|
|
|
|
|
|
|
|
Señalamiento Vertical (contrato no. 077) |
|
|
4,757.00 |
9,224,318.55 |
4,757.00 |
100.00 |
100.00 |
Señalamiento Vertical (contrato no. 086) |
|
|
4,757.00 |
8,824,900.90 |
4,757.00 |
100.00 |
100.00 |
|
|
|
|
|
|
|
|
Conservación Rutinaria de Puentes (contrato no. 016) |
|
|
213.00 |
6,610,187.32 |
213.00 |
100.00 |
100.00 |
Conservación Rutinaria de Puentes (contrato no. 017) |
|
|
150.00 |
6,778,841.95 |
150.00 |
100.00 |
100.00 |
Conservación Rutinaria de Puentes Adeudo 2018 |
|
|
finiquito |
350,556.77 |
|
|
100.00 |
|
|
|
|
|
|
|
|
Estudios y/o Proyectos |
|
|
|
10,000,000.00 |
|
|
34.28 |
Estudios y/o Proyectos |
|
|
|
14,350,000.00 |
|
|
86.71 |
Seguimiento |
|
|
|
3,260,719.00 |
|
|
100.00 |
Seguimiento |
|
|
|
3,260,719.00 |
|
|
96.68 |
|
|
|
|
|
|
|
|