SUBSECRETARIA DE INFRAESTRUCTURA |
DIRECCION GENERAL DE CONSERVACION DE CARRETERAS |
Programa Nacional de Conservación de Carreteras |
Avance Fìsico - Financiero |
|
|
|
|
|
|
DICIEMBRE2019 |
NOMBRE DE LA OBRA |
UBICACIÓN |
META |
ASIGNACION |
AVANCE FISICO |
AVANCE FINANCIERO |
Km Inicial |
Km Final |
UNIDAD |
% |
TLAXCALA |
|
|
|
646,030,746.01 |
|
97.53 |
83.11 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Aguanaja II (Tlaxcala - Belen) |
8+350 |
1.00 |
5,000,000.00 |
1.00 |
100.00 |
92.11 |
Las Colmenas I (Calpulalpan - Mazapa) |
4+250 |
1.00 |
13,500,000.00 |
1.00 |
100.00 |
92.18 |
Las Colmenas II (Calpulalpan - Mazapa) |
5+200 |
1.00 |
15,766,799.44 |
1.00 |
100.00 |
96.92 |
P. P. Unidad Sta. Cruz (Tlaxcala - Belen) |
4+000 |
1.00 |
6,000,000.00 |
1.00 |
100.00 |
100.00 |
Atlihuetzia III (Paso por Atlihuetzia) |
0+300 |
finiquito |
36,618.56 |
|
|
100.00 |
Calpulalpan (Lím Edos Mex./Tlax. - Calpulalpan) |
0+700 |
finiquito |
196,582.00 |
|
|
100.00 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Fresado de 5.0 cm y Carpeta de 5.0 cm |
|
|
15.07 |
34,922,000.00 |
15.07 |
100.00 |
100.00 |
Ramal a Tetlatlahuaca - Santa Ana Chiautempan * |
0.00 |
16.00 |
15.07 |
34,922,000.00 |
15.07 |
100.00 |
100.00 |
|
|
|
|
|
|
|
|
Renivelación y Carpeta de 5.0 cm |
|
|
26.80 |
81,846,490.74 |
26.80 |
100.00 |
100.00 |
Lím. de Edos. Pue./Tlax. - El Molinito (Cpo. A)Mezcla de alto desempeño |
9.00 |
29.70 |
20.70 |
60,208,490.74 |
20.70 |
100.00 |
100.00 |
Apizaco - Lím. de Edos. Tlax./Pue. (Tejocotal) (2 Cpos)T.A. |
19.80 |
23.90 |
6.10 |
21,638,000.00 |
6.10 |
100.00 |
100.00 |
|
|
|
|
|
|
|
|
Recuperación de 15.0 cm y Carpeta de 8.0 cm |
|
|
2.00 |
7,504,000.00 |
0.00 |
0.00 |
100.00 |
Apizaco - Lím. de Edos Pue./Tlax. |
17.80 |
19.80 |
2.00 |
7,504,000.00 |
0.00 |
0.00 |
100.00 |
|
|
|
|
|
|
|
|
Base de 15.0 cm y Carpeta de 5.0 cm |
|
|
0.56 |
1,318,000.00 |
0.56 |
100.00 |
99.98 |
Ramal a Lázaro Cárdenas |
24.20 |
24.76 |
0.56 |
1,318,000.00 |
0.56 |
100.00 |
99.98 |
|
|
|
|
|
|
|
|
Carpeta de 5.0 cm |
|
|
1.70 |
4,092,000.00 |
1.70 |
100.00 |
100.00 |
Los Treboles - Tlaxcala |
0.00 |
1.70 |
1.70 |
4,092,000.00 |
1.70 |
100.00 |
100.00 |
|
|
|
|
|
|
|
|
Microcarpeta |
|
|
9.86 |
14,349,000.00 |
9.86 |
100.00 |
100.00 |
Apizaco-Lim. de Edos. Pue./Tlax |
25.00 |
34.86 |
9.86 |
14,349,000.00 |
9.86 |
100.00 |
100.00 |
|
|
|
|
|
|
|
|
Renivelación y Riego de Sello |
|
|
110.81 |
114,951,000.00 |
110.81 |
100.00 |
99.99 |
Libramiento Tlaxcala (San Martin Texmelucan Apizaco) 2 Cpos. |
0.00 |
11.60 |
23.20 |
21,631,000.00 |
23.20 |
100.00 |
100.00 |
Lím. de Edos. Pue./Tlax. - El Molinito (Cpo. B) |
6.00 |
29.72 |
23.72 |
35,230,000.00 |
23.72 |
100.00 |
100.00 |
Los Reyes - Zacatepec (2 Cpos) |
112.00 |
115.00 |
6.00 |
6,882,000.00 |
6.00 |
100.00 |
100.00 |
Ciudad Industrial Xicotencatl II |
0.00 |
23.74 |
23.74 |
22,950,000.00 |
23.74 |
100.00 |
100.00 |
La Venta (T.A.) |
3.90 |
17.78 |
11.98 |
13,149,000.00 |
11.98 |
100.00 |
99.99 |
San Felipe Hidalgo T.A. (0.00 - 6.855 y 7.686 - 10.50) |
0.00 |
10.50 |
9.67 |
7,249,000.00 |
9.67 |
100.00 |
99.97 |
Lím. Edos. Pue./Tlax. - El Molinito Cpos "A" y "B" T.A. |
4.80 |
9.00 |
5.40 |
4,804,000.00 |
5.40 |
100.00 |
99.98 |
Teolocholco - Acuitlapilco |
0.00 |
7.10 |
7.10 |
3,056,000.00 |
7.10 |
100.00 |
99.97 |
|
|
|
|
|
|
|
|
Conservación Periódica de Puentes |
|
|
3.00 |
3,200,000.00 |
3.00 |
100.00 |
97.64 |
Conservación Periódica de Puentes |
|
|
5.00 |
4,000,000.00 |
5.00 |
100.00 |
89.72 |
Conservación Periódica de Puentes |
|
|
14.00 |
2,300,000.00 |
14.00 |
100.00 |
78.57 |
Conservación Periódica de Puentes |
|
|
1.00 |
3,000,000.00 |
1.00 |
100.00 |
100.00 |
|
|
|
|
|
|
|
|
Conservación Rutinaria de Tramos (Lineal del Estado) |
|
|
560.57 |
39,824,069.54 |
560.57 |
100.00 |
99.02 |
Finiquitos 2018 |
|
|
finiquito |
3,883,441.52 |
|
|
95.68 |
Gastos de Operación |
|
|
|
2,493,096.27 |
|
|
100.00 |
|
|
|
|
|
|
|
|
Señalamiento Horizontal (Lineal del Estado) |
|
|
560.57 |
15,235,426.20 |
560.57 |
100.00 |
100.00 |
Finiquito 2018 |
|
|
finiquito |
153,481.74 |
|
|
0.00 |
|
|
|
|
|
|
|
|
Barrera de Protección (contrato no. 028) |
|
|
3,600.00 |
9,425,445.00 |
3,600.00 |
100.00 |
100.00 |
|
|
|
|
|
|
|
|
Señalamiento Vertical (contrato no. 029) |
|
|
1,720.00 |
5,889,454.50 |
1,409.00 |
81.92 |
99.30 |
Señalamiento Vertical (contrato no. 030) |
|
|
1,720.00 |
6,701,299.63 |
1,410.00 |
81.98 |
100.00 |
Finiquito 2018 |
|
|
finiquito |
18,065.87 |
|
|
0.00 |
|
|
|
|
|
|
|
|
Conservación Rutinaria de Puentes (contrato no. 029) |
|
|
92.00 |
3,313,693.99 |
92.00 |
100.00 |
100.00 |
Conservación Rutinaria de Puentes (contrato no. 030) |
|
|
94.00 |
3,198,397.00 |
94.00 |
100.00 |
98.54 |
Finiquito 2018 |
|
|
finiquito |
46,621.01 |
|
|
100.00 |
|
|
|
|
|
|
|
|
Estudios y/o Proyectos |
|
|
|
500,000.00 |
|
|
100.00 |
Estudios y/o Proyectos |
|
|
|
13,400,000.00 |
|
|
100.00 |
Seguimiento |
|
|
|
1,830,699.00 |
|
|
100.00 |
|
|
|
|
|
|
|
|
(APP Texcoco- Zacatepec) |
|
|
294.06 |
226,885,064.00 |
|
|
53.59 |
|
|
|
|
|
|
|
|